Lenenergo completes modernisation of Koltushi substation

Russia, Vsevolozhsky District: Modernisation of the energy source will create conditions for the development of 10 kV distribution network in the area and allow new consumers to connect to the network.

 


6a501db6788f8bc3147fbec59d7a4924

6a501db6788f8bc3147fbec59d7a4924

Russia, Vsevolozhsky District: Modernisation of the energy source will create conditions for the development of 10 kV distribution network in the area and allow new consumers to connect to the network.

Koltushi substation was built in 1979 and its equipment was dated. This has been even greater problem since new houses were built in the area, reports Energy Land.

Lenenergo experts installed new power transformers, increasing from 80 to 126 MVA. Substation control building was also built, where switchgear of 6 and 10 kV was installed and relay protection and automation system. At the final stage of reconstruction, current and voltage transformers were installed.

Source: Energy Land