$48M substation expansion underway

USA, Ohio: FirstEnergy is expanding a substation in Wampum, Pennsylvania to accommodate new high-voltage electrical equipment designed to reinforce the regional electric system and enhance service reliability.

 


USA, Ohio: FirstEnergy is expanding a substation in Wampum, Pennsylvania to accommodate new high-voltage electrical equipment designed to reinforce the regional electric system and enhance service reliability.

The $48 million project includes the installation of voltage-regulating equipment – power transformers, capacitor banks, circuit breakers, communications equipment and a small control building, the utility said in a statement.

This voltage-control project is part of FirstEnergy’s $4.2 billion “Energizing the Future” transmission initiative.

The work at the Hoytdale substation is expected to be completed by early June.

Source: FirstEnergy