DEME Offshore has won a contract to transport and install equipment for two substations for the Hollandse Kust offshore wind farms.

 


GEC Solar

Image source: OE Offshore Engineer

Belgium, Zwijndrecht: DEME Offshore has won a contract to transport and install equipment for two substations for the Hollandse Kust offshore wind farms.

The wind farms are located in the Dutch sector of the North Sea.

The company will supply and install jackets, topsides and scour protection for both substations, which will be installed at the Hollandse Kust wind farms.

The contract has been awarded by the joint venture ENGIE Solutions-Iemants (a subsidiary of Smulders) that is responsible for the engineering, procurement, construction and offshore installation of the two substations.

Installation of the scour protection and jacket for Hollandse Kust is planned for the second half of 2021, while the topside for Hollandse Kust and jacket for will be installed during the summer of 2022.

Around 40 % of the Netherlands’ electricity needs will come from offshore wind farms by 2030. TenneT will realize the grid connections for these wind farms.

Bas Nekeman, Business Unit Director at DEME Offshore, said: “We are very pleased with the trust one of the most experienced leaders in offshore substation construction has again placed in DEME Offshore. The combination of ENGIE Solutions-Iemants’ extensive know-how, combined with our expertise in tailored solutions for the offshore wind industry, has proven to be successful in the past few years when we have worked closely together to achieve challenging projects such as the SeaMade and Moray East offshore wind farms.”

 

Source: OE Offshore Engineer