Končar GIM signs agreement for Gratkorn power plant

Croatia, Zagreb: Končar – Generators and Motors (GIM) has announced signing an agreement with the Austrian power company.

 


Image source: Končar

Croatia, Zagreb: Končar – Generators and Motors (GIM) has announced signing an agreement with the Austrian power company.

For the past several years, the Austrian power company has been planning to build a new Gratkorn hydro power plant  on the Mura River in the vicinity of Graz. However, due to a challenging process of obtaining all necessary permits, the commencement of the project has been postponed several times. GIM took part in the preparation of the project by providing support with respect to the optimization of the technical generators’ characteristics of the future power plant. At the beginning of 2020, a call for tenders for electromechanical equipment was published, where the equipment could also be offered in separate lots. GIM was one of the tenderers, and it was ultimately selected as the supplier of equipment and works.

The contracted scope of work also includes the delivery of two new generators, each with a power of 7 MVA, a speed of 107.14 rpm and a voltage of 5.3 kV, a contactless excitation system of the company KONČAR – Electronics and Informatics, spare parts, special tools and devices used for equipment installation and assembly, commissioning and pre-commissioning.

In addition, GIM also contracted the design and delivery of the first of three new replacement generators and associated equipment for HPP Ering-Frauenstein, located on the Inn River on the border between Germany and Austria. The second generator is expected to be ordered at the end of this year.

GIM is also in the process of realizing six other contracts for German and Austrian markets.

 

Source: Končar