Collett & Sons Ltd deliver two 160 T shunt reactors

UK, Scotland, Neart na Gaoithe: Collett & Sons have transported two 160 T shunt reactors over 8,046 km (5,000 mi).

 


Image source: Collett & Sons

UK, Scotland, Neart na Gaoithe: Collett & Sons have transported two 160 T shunt reactors over 8,046 km (5,000 mi). The shunt reactors were delivered to the onshore substation site for the Neart na Gaoithe offshore wind farm project, jointly owned by EDF Renewables and ESB.

Collett were contracted with the full scope of work providing a door-to-door service, including the project management, engineering and the transport of the two 160 T shunt reactors.

The shunt reactors were transported in three stages before arriving at the substation site. First, Collett worked in partnership with a trusted European partner to transport the shunt reactors ahead of their arrival in the UK. The Collett Projects Department were then responsible for all port operations including the loading of the vessel, also chartered by Collett, for the 7,724 km (4,800 mi) to the Port of Leith in Scotland.

Working closely with the port, Collett carefully planned the cargo’s discharge, including providing crane lifting plans and an agreed programme of works for all loading and discharge operations.

Once at the port, utilising an 800 T crane, the shunt reactors were discharged onto a dedicated 14-axle line modular flat top trailer. Both shunt reactors were offloaded at the port onto stools for temporary storage. Collett also transported and stored multiple ancillary components at their port side depot in Grangemouth.

Utilising their 550 T capacity girder bridge with 20-axle lines, Collett transported the shunt reactors from Leith Docks to Innerwick. Due to narrow access along the remainder of the route, Collett transhipped each of the two shunt reactors from the 20-axle girder bridge on to a 14-axle flat top modular trailer in a dedicated road closure area, complete with all traffic management, in order to complete delivery. All movements were facilitated under police escort, as well as Collett’s in-house fleet of pilot vehicles.

At the NnG onshore substation site, located in the Lammermuir Hills, Collett’s Heavy Lift Team offloaded and positioned the shunt reactors into their final position using a hydraulic jacking and skidding system.

Part two of the project is expected to take place in the coming weeks , when two 180 T supergrid transformers are due to be delivered to the wind farm site.

 

Source: Collett & Sons Ltd