New transformers for Braybrooke Substation

UK: Since early 2021 National Grid Electricity Transmission (NGET) has been building a new electricity substation near Braybrooke, Leicestershire.

 


transformer delivery

Image source: National Grid

UK: Since early 2021 National Grid Electricity Transmission (NGET) has been building a new electricity substation near Braybrooke, Leicestershire.

The new substation, once complete, will form a vital part of electrical infrastructure to support Network Rail’s electrification of the Midland Main Line.

Following months of hard work, the project has reached a major milestone, as the engineering team have taken delivery of two new transformers.

The transformers arrived during November and were delivered via an access road off Kettering Road built to ensure construction traffic avoids the areas of Market Harborough and Braybrooke. Weighing an impressive 100 T, they will now be installed at the substation over the coming months.

Braybrooke Substation will provide an interface between the railway and National Grid. It will take electricity from National Grid at 400 kV to a transformer which will then reduce the voltage to 25 kV. Network Rail will then take the electricity and distribute it up and down the railway line via a track side feeder station to electric trains running between London St Pancras and Market Harborough.

Electrifying the line is expected to bring significant benefits for rail passengers and people living nearby – enabling faster, more efficient, quieter and cleaner trains to operate on the line.

“This latest milestone is a huge step forward to both meeting our customer’s needs by providing a safe, secure and reliable supply of electricity and delivering on our commitment to decarbonisation. With the transformers now on site we are well on track for the new substation to be complete and operational by late next year,” said Luke Sewell, Project Engineer for National Grid.

 