#Paraguay


Construction works substation Paraguay

ANDE’s substation to get $26 M revamp

ANDE has reached 60 % completion of the expansion, modernization and interconnection works of the Alto Paraná substation, located in Ciudad del Este.

CG wins power equipment order in Paraguay

India, Mumbai: Avantha Group Company CG has signed a contract with the national power utility of Paraguay, Administración Nacional de Electricidad (ANDE), for the design, manufacturing, testing and supply of 245 kV, 72.5 kV and 23 kV switchgear equipment.

New transformer tested in the Hernandarias industrial park

Paraguay, Alto Paraná: The National Electricity Administration (ANDE) performed a test energization of a 220/23 kV transformer 41.6 MVA at the field of the future Hernandarias industrial park in Alto Paraná department.