Khabarovsk airport powering up with new transformer
Russia, Khabarovsk: The Khabarovsk branch of a Russian utility company DRSC is entering the final stages of the reconstruction of the 110 kV substation which feeds the Khabarovsk airport boundary.
Russia, Khabarovsk: The Khabarovsk branch of a Russian utility company DRSC is entering the final stages of the reconstruction of the 110 kV substation which feeds the Khabarovsk airport boundary.
Russia, Khabarovsk: The substation 110/35/6 kV feeding the Khabarovsk Novy Airport will be upgraded with the third power transformer at a cost of over $2,5 million (171 million rubles).
Russia, Khabarovsk: Russia’s Federal Grid Company (FGC) will provide electrical infrastructure to the territory of advancing social and economic development a specially created advanced economic zone (TOSER), in the Khabarovsk territory.