Permenergo to reconstruct substation Kochkino
Russia, Perm Krai: Permenergo is currency reconstructing the 110/10 kV substation Kochkino, where power transformers are being installed.
Russia, Perm Krai: Permenergo is currently reconstructing the 110/10 kV substation Kochkino, where power transformers are being installed.
The total cost of a power facility reconstruction will be more than RUB 500 million ($12.3 million), reports EJ News. Two power transformers, which have recently been delivered, are of 16 MVA each and are manufactured by SVEL.
Source: EJ News
#Kochkino power transformers#Kochkino substation#Kochkino substation reconstruction#Permenergo power transformers#Permenergo substation