United Electric Grid of Moscow upgrading one of main substations in the centre

United Electric Grid of Moscow has completed the next stage of upgrading one of the key substations in the city centre - the 220/110 kV Presnya of the Central Electric Network.

 


9911ecbea07a30e7c89fdadbe8a058e8

9911ecbea07a30e7c89fdadbe8a058e8

United Electric Grid of Moscow has completed the next stage of upgrading one of the key substations in the city centre – the 220/110 kV Presnya of the Central Electric Network.

The reconstruction began in 2007 and its completion has been planned for 2018. Despite the decline in investment financing, the company maintains the pace of reconstruction of all its facilities. Preliminary estimated total cost of the Presnya substation upgrade, which will include the power transformer replacement, is 4 billion rubles ($ 120 million).