TCN receives 8 transformers

The Transmission Company of Nigeria (TCN) receives eight new power transformers under its Project Management Unit at the Apapa Port, Lagos.

 


Image source: 21st Century Chronicle

Mrs Ndidi Mbah, General Manager Public Affairs stated in a statement in Abuja that the Transmission Company of Nigeria (TCN) stated it has received eight new power transformers under its Project Management Unit at the Apapa Port, Lagos.

Mbah said that the transformers were six 150/187.5 Mega Volt Ampere (MVA), 330/132/33 Kilo Volt (kV) power transformers and two 100/125MVA, 132/33kV power transformers.

She stated that the transformers were still at the port, and that arrangement was being concluded to move them out.
Mbah listed the suggested locations for the transformers to include Bauchi- 2×150/187.5MVA, 330/132/33kV.

1×150/187.5MVA, 330/132/33kV – Mayo Belwa, 1×150/187.5MVA, 330/132kV – Yola and 1×150/187.5MVA, 330/132/33kV —Maiduguri.

1×150/187.5MVA, 330/132/33kV – Damaturu, 2×100/125MVA, 132/33kV – Yola, ” she added.
According to Mbah, TCN through the contractor, MBH will move all the transformers to TCN Substations mentioned above.

She also said that the project was one of the World Bank-funded projects under Nigeria Electricity Transmission Project (NETAP).

Source: 21st Century Chronicle